Technology Utilization
2008 - 09  First Semester
August 2008  thru  January 2009
Investment Project Schedule
First Marking Period Second Marking Period Investment Project Data
First Marking Period
Each team must execute at least two trades between  Sep 19  and  Oct 23.
Event Notes & Comments Due   Date  
                     
    Form Teams Form teams and create team name Thu, Sep 04  
    Purchase Request Spend at least $30,000 to buy between 2 and 5 companies Thu, Sep 11  
    Initial Stock Purchase Stock will be purchased after the stock market closes Fri, Sep 12  
    Purchase Summary Summarize initial purchase Mon, Sep 15  
    Portfolio Valuation Day # 1 Valuation report is due the following Tuesday Fri, Sep 19  
    Portfolio Valuation Day # 2 Valuation report is due in two school days Fri, Sep 26  
    Portfolio Valuation Day # 3 Valuation report is due in two school days Fri, Oct 03  
    Portfolio Valuation Day # 4 Valuation report is due in two school days Fri, Oct 10  
    Portfolio Valuation Day # 5 Valuation report is due in two school days Fri, Oct 17  
    Last day that trades are permitted For this marking period Thu, Oct 23  
    Portfolio Valuation Day # 6 Valuation report is due in two school days Fri, Oct 24  
    Last day reports will be accepted for this marking period Thu, Oct 30  
    No Valuation Marking period break Fri, Oct 31  
                     
    End of First Marking Period     Fri, Oct 31
Second Marking Period
Each team must execute at least two trades between  Oct 24  and  Jan 06.
Assignment Notes & Comments Due   Date  
                     
    Portfolio Valuation Day # 7 Valuation report is due in two school days Fri, Nov 07  
    Portfolio Valuation Day # 8 Valuation report is due in two school days Fri, Nov 14  
    No Valuation Thanksgiving holiday Fri, Nov 21  
    Portfolio Valuation Day # 9 Valuation report is due in two school days Fri, Nov 28  
    Portfolio Valuation Day # 10 Valuation report is due in two school days Fri, Dec 05  
    Portfolio Valuation Day # 11 Valuation report is due in two school days Fri, Dec 12  
    No Valuation Winter vacation break Fri, Dec 19  
    Last day that trades are permitted for the investment project Tue, Jan 06  
    Portfolio Valuation Day # 12 Valuation report is due in two school days Wed, Jan 07  
    End of Invest Project   Wed, Jan 07  
    Last day reports will be accepted for the investment project Mon, Jan 12  
                     
    End of Second Marking Period     Mon, Jan 12
Notes:
All dates are subject to change.
A conscientious attempt will be made to keep this schedule up-to-date.
Questions may be emailed to:  Dr. Dave Schonbach Updated: 14-Sep-08